Six labourers split between clearing soil at the columns and tying wall steel. The engineer was asked to inspect regularly. 25 mm bars were required up to slab level.
Sunday · site work
Sunday · site work
Six labourers split between clearing soil at the columns and tying wall steel. The engineer was asked to inspect regularly. 25 mm bars were required up to slab level.