The bar gang left incomplete work at three in the morning and returned after seven. Floor and fittings were cleaned, staircase steel tied and chairs bound to the bottom mat. A puja was held, then the floor slab was cast: 116.5 cubic metres of ready-mix across six vehicles, completed successfully by late evening.
Sunday · site work