A second tractor of sand arrived and 16.5 cubic metres of concrete was booked for the wall. A power cut from eleven was restored at half past two. Walls and columns were corrected for plumb and line, with one column 15 mm out. A generator was discussed, and the pump and loading were set for the next morning.