The JS Legacy23 September 2026
Site photograph, 23 September 2026

Wednesday · site work

23September
2026

After 22 hours the tank showed no leak and the waterproofing passed. A fifteen foot ladder was needed after the excavation, an excavator was hired for three and a half hours, and the street lights were found not working.

9 photographs