The civil team worked but the ready-mix pipe line was not laid until late morning, so the wall pour started late and ran into the night. The formwork board burst, the pour was stopped and restarted from the ramp side, and half was done by nine in the evening. Food was arranged for the crew.
Wednesday · site work