The engineer inspected the site. Raft corner bars were to be tied top and bottom, cleaning and brick removal were ordered, and the slab was fixed at 150 mm thick with double 8 mm mesh at 200 mm centres. The cast lift well and tank were measured and found within a few millimetres. About 54 cubic metres of concrete was planned for the next morning.
Thursday · site work