Casting was planned for the next day and 17 cubic metres of M30 was ordered. A pump was arranged for the water. Cover and wall thickness faults were found in the formwork and the wall layout was to be corrected.
Friday · site work
Friday · site work
Casting was planned for the next day and 17 cubic metres of M30 was ordered. A pump was arranged for the water. Cover and wall thickness faults were found in the formwork and the wall layout was to be corrected.