The JS Legacy17 June 2026
Site photograph, 17 June 2026

Wednesday · site work

17June
2026

River sand was to be laid before the pour. The area was measured at about 2,000 square feet, ordered as 21 cubic metres in three trucks, and the termite treatment was completed.

2 photographs